September 13, 2013

Delays, cost overruns plague water projects

In the past decade, Jeff Drager has watched his two daughters grow up, graduate from high school and college and start their first jobs. Yet he’s still stuck on the same project at work – winning state and federal approval to build a new water reservoir.

Begun in 2003 and scheduled to be up and running by 2011, the Windy Gap Firming Project, like many others across the state, still is mired in regulatory delays.

Whether or when Windy Gap – a project designed to serve more than a dozen entities including Longmont, Lafayette, Louisville, Superior, Erie and Broomfield – will be built is still unclear 10 years after the first regulatory review took place.

SPONSORED CONTENT

Exploring & expressing grief

Support groups and events, as well as creative therapies and professional counseling, are all ways in which Pathways supports individuals dealing with grief and loss.

Drager, an engineering project manager with the Northern Colorado Water Conservancy District, is in charge of bringing Windy Gap online. The project includes building Chimney Hollow Reservoir, one ridge over from Carter Lake in the foothills outside Loveland. It is designed to help Northern Water better manage and store water it developed in 1985.

Northern is working with 13 Northern Colorado water providers to develop the latest phase of Windy Gap, which is designed to serve 60,000 households. It initially submitted the project for environmental review to the U.S. Bureau of Reclamation in 2003. Through the National Environmental Policy Act, or NEPA, a project’s environmental impacts are reviewed during several stages of technical analysis and public comment. A 2005 Northern Water fact sheet projected a final “record of decision” could come by the end of that year, meaning construction could start soon after and the reservoir would be ready by 2011.

That forecast was wildly optimistic. The bureau didn’t issue a final environmental impact statement, a key step in NEPA, until late 2011. Reviews by federal and state scientists, environmental groups and western Colorado interests each triggered calls for mitigation and changes that added months and then years of delay.

“Nobody would have anticipated some of these things” said Drager.

Project partners have spent $12 million to date just on permitting, agreed to pay millions more than expected for environmental mitigation and watched the total project cost estimate jump nearly 28 percent, from $223 million to $285 million. That’s roughly $1,033 per household.

Similar delays and cost overruns have plagued nearly every other major Colorado water-development project that has sought regulatory approval since the 1990 defeat of Two Forks Dam. Proposed by Denver Water, the $1 billion Two Forks project passed through NEPA with government approval before the Environmental Protection Agency vetoed the decision because of study inadequacies and unresolved water-quality impacts.

After more than a decade of drought and a new wave of growth, water utility planners believe the project review system is broken and must be fixed. Legal experts and environmental watchdogs say the projects themselves are outdated in concept and that utilities need to rethink how they obtain, store and deliver water.

Drager has had to ask Windy Gap Firming Project partners for an extra $1 million four separate times in the past five years to pay for unexpected mitigation. Consideration of the upper Colorado as a federally designated wild and scenic river triggered additional analysis. State fish and wildlife managers required further mitigation plans, including a study for a fish bypass around Windy Gap Reservoir. The project will take flows from the Colorado River, so Northern Water had to agree to enhance river habitat and operate water diversions to support endangered fish. The EPA filed comments that led to further changes. When an end seemed near in June 2012, Grand County exercised its “1041 powers,” requiring a new permit and an agreement from partners to improve clarity for Grand Lake, which has deteriorated in part because of Northern’s water diversions. Now mostly settled, the Grand Lake revision marked the fifth major project stoppage.

“It’s not just NEPA,” Drager said. “There are a whole bunch of federal requirements – the Endangered Species Act, the Clean Water Act – and then you’ve got a group of state laws which don’t always work well with the federal laws. So, it’s very hard to know when is the last step. When are you done?”

Communities and water districts that are footing the bill have weathered the delays and tacked-on costs so far.

The city and county of Broomfield has used money from water tap fees for its share of the project and paid the additional costs with reserve funds stashed away for such purposes, said public works director David Allen. But even with the added mitigation and expenses, managers say the project remains an inexpensive and preferred alternative to purchasing shares in existing water projects, such as the Colorado-Big Thompson system or buying out farmers’ water rights and drying up local agriculture.

Since Two Forks, federal agencies involved with NEPA reviews are “gun shy,” said Dave Little, planning director for Denver Water, which also has spent more than 10 years seeking approval for its own major water project, the Moffat Collection System.

The Moffat project would expand Gross Reservoir, southwest of Boulder, and fill it with flows diverted from the Fraser River near the Continental Divide. But progress has been slow, Little said, as government consultants have conducted detailed studies and assessments of low-probability or marginal scenarios. As an example, Little mentioned a “full-blown” environmental assessment that had to be done on the utility’s southern reservoir operations, which are located 100 miles from Gross Reservoir and would be minimally altered by the Moffat project. Such detours have contributed to Moffat’s estimated price tag doubling to $280 million since formal review began a decade ago.

Jim Lochhead, Denver Water chief executive, said he hopes the process can be improved and perhaps expedited.

“We’re committed to doing this the right way, but we seem caught in this series of processes that really inhibit our ability to meet the needs of our customers,” he said. “Circumstances are changing much more rapidly than in the past, and we have a very rigid regulatory process that is not nimble, adaptable or capable of allowing for critical, timely decisions on key infrastructure.”

Part of the problem also may stem from agencies lacking the personnel and resources to effectively perform reviews. This summer, Northern Water gave the Army Corps $140,000 for a project manager position to keep moving forward with review of the Northern Integrated Supply Project, which would build Glade and Galeton reservoirs to serve up to 80,000 new households in the region.

Drew Beckwith compares large water projects to the lyrics of sad country-western songs: They’re always late and in need of money. They don’t live up to expectations and they’re risky. Beckwith, who works for Boulder-based conservation group Western Resource Advocates, said he believes the delays and overruns are more indicative of a planning issue than a process problem.

“It’s no surprise that the environmental-review process takes a long time,” he said. “These are big, complex projects that have lots of impacts on communities and the environment, and it’s appropriate to take a long hard look.”

In the past decade, Jeff Drager has watched his two daughters grow up, graduate from high school and college and start their first jobs. Yet he’s still stuck on the same project at work – winning state and federal approval to build a new water reservoir.

Begun in 2003 and scheduled to be up and running by 2011, the Windy Gap Firming Project, like many others across the state, still is mired in regulatory delays.

Whether or when Windy Gap – a project designed to serve more than a dozen entities including Longmont, Lafayette, Louisville, Superior, Erie and Broomfield – will be…