BOULDER — A U.S. District Court judge last week dismissed a 2024 lawsuit filed by the City of Boulder against the Federal Aviation Administration that city officials had hoped would allow them to defy the feds and close the Boulder Municipal Airport and build housing on the site.

In her dismissal order, which has won praise from some Boulder business leaders, Judge Nina Wang wrote that she was not tossing the case based on a review of its merits. Rather, Wang dismissed the lawsuit without prejudice — meaning Boulder could appeal or refile — “(b)ecause the City has not met its burden to establish its standing.”

Boulder officials had demanded that a judge release the city from its FAA-mandated obligation to operate the airport in perpetuity. That obligation, the FAA argued, results from the acceptance of grant funding decades ago to purchase portions of the airport site.

The city acknowledged that certain FAA grants come with a 20-year commitment to continue airport operations. Since Boulder stopped accepting grants only five years ago, the earliest it could be free of its obligations could be 2040.

In its arguments to the court, Boulder “concedes that any ‘additional regulatory burden’ will not be realized until 2040, when the most recent grant agreement expires and if the United States continues to maintain that the Airport must be operated in perpetuity. Moreover, the City does not allege any present intention to accept federal grants, instead resolving to not accept any additional funds until 2040,” Wang’s dismissal order reads. “Because any declaratory relief the Court could issue would not have any real-world impact until 2040 — beyond providing the City satisfaction of a favorable ruling — the Court finds that the City has not demonstrated that it has an injury that would be redressed by a favorable decision.”

A Boulder spokesperson told BizWest that “we are evaluating the ruling and assessing our legal options.”

Tucked away on about 180 city-owned acres between neighborhoods and business parks in east Boulder, the Boulder Municipal Airport, or BDU, property has been identified by housing advocates as a prime location for the development of below-market-rate homes. Because the city owns the airport land, it could, in theory at least, provide parcels to developers on the cheap in exchange for a pledge to build less expensive homes.

Boulder’s median sales price for single-family homes in August was nearly $1.39 million.

A pair of 2024 ballot initiatives that, if passed, would have closed the airport for the purpose of building housing on the site were pulled prior the election by their organizers after the city sued the FAA.

While few argue that Boulder wouldn’t benefit from additional housing options for workers and families, the airport decommissioning plan hasn’t lacked for critics — beyond the FAA — many of whom argue that the proposal isn’t feasible and could prove economically harmful both to businesses and city coffers. The negative impact on Boulder’s budget may come to fruition sooner rather than later, as Judge Wang’s lawsuit dismissal ordered the city responsible for the FAA’s court costs.

Boulder Municipal Airport, according to the Colorado Department of Transportation’s 2020 Colorado Aviation Economic Impact Study, the most recent dataset of its kind, supports 299 jobs and is responsible for nearly $97.8 million in total economic impact. That metric includes payroll, business revenues and contributions to gross regional product from both on-site businesses and visitors who travel through BDU.

“The Boulder Chamber has been very clear in the need to preserve the Boulder Municipal Airport as a center for our mobility future,” chamber CEO John Tayer told BizWest. Chamber leadership “urges the City of Boulder to drop the lawsuit and return to the pursuit of federal funding for maintenance of this facility.”

Jan Burton, a pilot who flies out of BDU and a member of Boulder Aviation Association, an airport advocacy group, wrote in an email to BizWest that “(s)urvey after survey shows that the Boulder Municipal Airport is valued by most residents in Boulder. The fact that the City undertook a wasteful lawsuit to accommodate a small, vocal group is representative of poor financial decision-making.  With the City’s finances already strained to the point of hiring freezes and existing programs going un-funded, it would be poor governance for the City to consider putting more resources into this lost cause of suing the FAA. They should immediately resume accepting grants from the FAA and the Colorado Department of Transportation to avoid having to pay millions of local tax dollars out of the general fund for airport upkeep. …Instead of wasting money on lawsuits and consultants, why not put the resources to work right here at the airport to benefit the community directly?”

Some critics of decommissioning the airport have pointed to the Area III Planning Reserve as a more-appropriate location for construction of city-supported housing.

Created in 1993 with an eye toward Boulder’s future growth needs, the Area III Planning Reserve sits on 493 acres just north of U.S. Highway 36. The city owns nearly 220 acres — of that, nearly 190 acres was purchased for the purpose of building an urban park and about 30 acres were purchased with affordable housing funds — with most of the remainder held privately.

It’s in the interests of both city and business leadership to “identify other appropriate locations and opportunities (other than the BDU site) for the diverse mix of housing options for our workforce,” Tayer said, which could include “the use of our lower density commercial areas” for new residential projects and/or the development of Area III.

The lawsuit is City of Boulder v. United States of America et al, case number 1:24-cv-02057, filed July 28, 2024 in U.S. District Court in Colorado.

A U.S. District Court judge last week dismissed a 2024 lawsuit filed by the City of Boulder against the Federal Aviation Administration that city officials had hoped would allow them to defy the feds and close the Boulder Municipal Airport and build housing on the site.

Lucas is an award-winning journalist who worked at news agencies from Maryland to Wyoming to South Carolina before putting roots down in Colorado.